Cell Impact is building up its business in two phases. Phase I involved quickly securing enough capacity to initially meet the needs of customers and capture business opportunities. It also involved building a larger factory and acquiring new production equipment. In Phase II, the focus is on greatly reducing production costs through a higher degree of automation and smarter processes in addition to being able to handle growing volumes.
2018 - 2019 | New strategy – get started
- Cell Impact becomes a flow plate producer
- Begins flow plate production; highly focused on selected customers
- Approximately 15 employees
2020 | Phase I - new facility, scale-up
- Moved to new 6,000 m2 factory
- Phase-I production build-up with 2,500 m2 production area
- Ramping up production – North American accounts drive volumes
- Approximately 30 employees
2021 | Accelerate, ramp-up production
- EU’s Green Deal triggers enquiry inflow
- Major Plug Power order
- Ramping up production
- +100 employees with 25 engineers/technicians
- Initiate Phase-II – an additional 2,500 m2 to reach 5,000 m2 production area
2022 | Phase II – new productive process technology, accelerate
- New concepts and some new processes developed
- Straightforward and automated process flows for higher productivity
- Significant increase in production area established and gradually popularized with new equipment in response to demand
- Began to introduce new compact, automated process technology
- The experiences from Phase l and the realization of the future plan during Phase ll represent a strong offer in an accelerating industry
2023 - | Internationalization
As technology for the hydrogen society is connected to security and industrial policy, localization may become increasingly important. Cell Impact stands ready with factory-in-factory concepts that can be a model for supporting customers locally. Cell Impact Forming™, which is comparatively very easy to build and install, is an important building block here.